|
Who |
Josiah Wedgwood & Sons Ltd and Hough Engineering Ltd |
|
When |
30 March 07 |
|
Where |
Stoke on |
|
Why |
Hough Engineering Ltd was fined £20,000 and costs of £10,000 at Stoke on Trent Crown Court following an accident which resulted in Mr Andrew Cotton, an employee, falling 6.2 metres through a fragile skylight. Mr Cotton sustained serious injuries including multiple fractures. Josiah Wedgwood and Sons Ltd were also prosecuted and fined £60,000 and costs of £17,837 for contracting Hough Engineering Ltd to undertake work to a warehouse when they failed to control of the contractors at this remote site. Prosecuting HSE Inspector, David Brassington said: "Experience shows that falls from height usually occur as a result of poor management control rather than because of equipment failure. On this occasion the roof repair activity was allowed to commence without the provision of any precautions, such as close hung safety nets and platforms with edge protection, which would have prevented the fall. Companies need to realise the necessity of implementing appropriate safety measures and management systems to provide a safe working environment, preventing falls and avoiding injury." The accident occurred on 6 May 2003 when Mr Andrew Cotton from |
|
How Much? |
£80,000 plus costs across the 2 parties |
|
Who |
Guy Leasing Ltd and James Walsh |
|
When |
30 March 07 |
|
Where |
|
|
Why |
A |
|
How Much? |
£12,000 plus costs across the 2 parties |
|
Who |
Adis Scaffolding Ltd |
|
When |
29 March 07 |
|
Where |
|
|
Why |
Adis Scaffolding Limited of Duckmanton, |
|
How Much? |
£10,000 plus costs |
|
Who |
Tex Industrial Plastics Ltd |
|
When |
29 March 07 |
|
Where |
|
|
Why |
The Health and Safety Executive (HSE) is warning firms to make sure adequate training and supervision is in place for staff involved in unfamiliar tasks following a serious incident at Tex Industrial Plastics Ltd 'Factory 2' on Wetherby Road, Derby. The incident happened on 10 February 2006 when Christopher Bird, aged 36, from |
|
How Much? |
£3,235 plus costs |
|
Who |
|
|
When |
28 March 07 |
|
Where |
|
|
Why |
Durham County Council was fined a total of £20,000 today for five health and safety offences arsing from an incident in which a 100-tonne mobile crane overturned into a culvert where men were working. The incident occurred on 1 August 2005 in Front Street, Pelton Fell, County Durham, when the council was constructing an extension to an existing culvert and repairing the head wall of the culvert. HSE Inspector Michael Brown said: "The council ordered a crane and operator from contractors to lower materials into the culvert where they were working, which was about 30 metres below road level. A 60-tonne crane was sent to the site but did not have sufficient reach, so a 100-tonne crane was sent. Its outriggers were placed on the earth at the top of the embankment where there was insufficient bearing capacity. The ground gave way and the crane toppled into the culvert. It missed the five men working in the culvert by no more than five metres. "The site manager had been called away and the foreman who was left in charge did not have training or knowledge of lifting operations, and the operation was not properly planned or adequately supervised. "In addition, a nearby public footpath from a housing estate to Front Street had not been closed off, though there is no evidence that members of the public were in the vicinity at the time". The council was fined £7,000 each for failing to ensure the safety of its employees; and failing to ensure that people affected by their work but not employed by them were not exposed to risks; and £2,000 each for failing to ensure every lifting operation was carried out in a safe manner; failing to ensure every lifting operation was appropriately supervised; and failing to ensure every lifting operation was properly planned. It admitted all the offences. The council was also ordered to pay £3,103 costs. |
|
How Much? |
£20,000 plus costs |
|
Who |
GDM Partnership Building Services Consultants Ltd |
|
When |
27 March 07 |
|
Where |
|
|
Why |
GDM Partnership Building Services Consultants Ltd were fined £15,000 and ordered to pay £4,230 in costs at Basingstoke Magistrates Court for breaches of Health and Safety legislation. The prosecution followed an investigation by the Health & Safety Executive into an incident that occurred on 1st June 2005 at an unoccupied commercial building at Jays Close, Basingstoke. Mr. David Prince was taking measurements of the flat roof when he fell from the edge - a height of approximately 6 metres. Apart from warning all staff to be careful, GDM took no measures to prevent their employees, including Mr Prince, from falling from the roof. Mr. David Prince from Tunbridge Wells, Kent, suffered fractures. GDM Partnership Building Services Consultants Ltd from |
|
How Much? |
£15,000 plus costs |
|
Who |
Bradgate Containers Ltd |
|
When |
27 March 07 |
|
Where |
Loughborough |
|
Why |
Bradgate Containers Ltd of |
|
How Much? |
£5,000 plus costs and compensation |
|
Who |
Jomast Developments Ltd |
|
When |
26 March 07 |
|
Where |
Teeside |
|
Why |
Jomast Developments Ltd, of Oriel House, |
|
How Much? |
£3,000 plus costs |
|
Who |
Bau Gmbh and ReConstruction UK Ltd |
|
When |
23 March 07 |
|
Where |
|
|
Why |
Bau GmBH, of Angelburg in |
|
How Much? |
£150,000 plus costs across the 2 parties |
|
Who |
Kevin Breithaupt |
|
When |
23 March 07 |
|
Where |
|
|
Why |
An asbestos analyst was fined £2,500 and ordered to pay £1,500 costs after pleading guilty to a criminal charge brought by the Health and Safety Executive (HSE) after he had issued a clearance certificate after removal of asbestos from the boiler room of a school. Kevin Breithaupt of Hindley Green, Wigan pleaded guilty to a breach of Section 7 of the Health and Safety at Work Act in that he produced a four stage clearance certificate following removal of asbestos, when asbestos was still present in the boiler room of Maryville Primary School in Prescot. Sarah Wadham, an HSE Inspector who managed the case says: "The risk to health from asbestos is well known and others may have been put at risk as they worked in the room following the issue of the certificate. Our investigation occurred after HSE received a complaint regarding the standard of the asbestos clean in the boiler room at the school. Knowsley Metropolitan Borough Council had organised for asbestos lagging to be removed from the boiler prior to the removal of the boiler room system. Following the asbestos removal Mr Breithaupt produced the certificate which was passed to the council and then onto the contractors who were to remove the boiler. Contractors started to work in the boiler room and became concerned about asbestos material left in the room. Three men - Donald Cowperthwaite, Francis Disley and John Appleton - worked in the room for about three hours until a decision was taken to stop work and query the amount of material left. Lockwoods Technical Services Ltd who were the Principal Contractor for the project commissioned a further asbestos survey and a further clean had to be done. “ |
|
How Much? |
£2,500 plus costs |
|
Who |
Royal United Hospital |
|
When |
20 March 07 |
|
Where |
|
|
Why |
Bath RUH NHS Trust was prosecuted at Bath Magistrates' Courts on 20 March, under the Control of Substances Hazardous to Health Regulations (COSHH) 2002, following the death of a patient (Daryl Eyles) in February 2004 from Legionnaires' disease contracted whilst he was a hospital in-patient. Sentencing took place at Bristol Crown Court on 29 March 2007. The Trust pleaded guilty to both charges and was fined £40,000 for Regulation 6 and £40,000 for Regulation 7 of the COSHH regulations. It was also ordered to pay full costs of £23,883. HSE Inspector, Susan Chivers, who investigated the case, said: "This prosecution sends a clear message to all NHS Trusts that they need to assess the risks of Legionella bacteria in their water systems and put in place measures which effectively reduce these risks. They particularly need to ensure that their risk assessment takes into account the vulnerability of certain patients, such as those with reduced immunity to infection. Keeping the risk assessment up-to-date is vital - so whenever changes to water systems or to the use of Trust buildings are planned, then risk assessments and control measures need to be updated accordingly. Additionally, control measures need to be properly monitored to ensure that they continue to be effective. Protecting the health and safety of patients, visitors and employees in this way is a responsibility Trusts must take seriously - not to do so can have fatal consequences." |
|
How Much? |
£80,000 plus costs |
|
Who |
North East Environmental Ltd |
|
When |
16 March 07 |
|
Where |
North Shields |
|
Why |
North East Environmental Ltd of |
|
How Much? |
£4,600 plus costs |
|
Who |
Ministry of Defence (Crown Censure) |
|
When |
16 March 07 |
|
Where |
HSE HQ |
|
Why |
The HSE called the Ministry of Defence to its |
|
How Much? |
not applicable |
|
Who |
E J Lidster and Sons Ltd |
|
When |
15 March 07 |
|
Where |
|
|
Why |
The Barnsley firm was fined £70,000 plus costs of £35,000 after a driver employed by the company was fatally injured by a falling excavator as he attempted to load it on to his flat bed lorry at a site in |
|
How Much? |
£70,000 plus costs |
|
Who |
R P Tyson Construction Ltd |
|
When |
13 March 07 |
|
Where |
|
|
Why |
Blackpool firm R P Tyson Construction Ltd received fines of £16,000 and were ordered to pay £6,446 costs at Preston Crown Court after pleading guilty to a charge under the Health and Safety at Work etc Act 1974 (HSW Act). The case followed the death of its employee Anthony Isherwood during construction work at Hutton Grammar School near Preston on 29 November 2004. HSE Inspector Roger Jamson said: "Tony Isherwood was working on the conversion of a gymnasium into classroom space following construction of a new gym elsewhere on site. Part of this work involved building a mezzanine floor supported by steel beams that had been put into place over the previous few days. Packs of corrugated steel floor decking had been temporarily placed on the beams ready to be laid out at a later date. In the morning Mr Isherwood had started fixing the beams into place but before this was completed he moved to ground level where, with others, he started to build a wall, intended to support the flooring between two of the beams. An all terrain lift truck was being used to bring materials into the gym. When this reversed its mast struck one of the steel beams, which was supporting a pack of floor decking, as one end of the beam had not been fixed into place this caused steel decking to fall onto Mr Isherwood and crush him. He died at the scene a short time after the incident. In common with many accidents the death of Mr Isherwood had a number of underlying causes, the identification of any one of these factors would have prevented this tragic incident. It is important that anyone in control of a construction site assesses the particular risks involved at their specific site of work and that this is kept up to date as circumstances change. " |
|
How Much? |
£16,000 plus costs |
|
Who |
University of the Arts |
|
When |
13 March 07 |
|
Where |
City of |
|
Why |
The Health and Safety Executive (HSE) warned firms of the risks of working at height without taking proper precautions following the serious injuries of a contractor and member of the public at the University of the Arts London. At a hearing on the 8th March 2007 at the City of London Magistrates Court, John Preston and Graham Cresswell were each fined £7,500 after pleading guilty to breaching Section 3(2) of the Health and Safety at Work etc Act 1974 (HSW Act) and the University of the Arts London was fined £20,000 (the maximum fine in the Magistrates Court) after pleading guilty to breaching Section 3(1) of the HSW Act. Costs of £9654 were awarded to HSE. HSE Inspector Dominic Long said, "This case should act as a wake up call to all firms engaged in working at height to properly consider the serious risks involved. This was an accident which very nearly killed a young man and a member of the public. The accident happened on one of the busiest shopping streets in the UK and it was sheer luck that more people were not killed or injured. It was entirely preventable - had the contractors and the University cooperated with each other in assessing the risks and planning the work being carried out it is very likely that this accident would have been avoided." Mr Jeremy Davenport suffered multiple injuries including a shattered heel and a broken pelvis when he fell over 5 metres from a ladder he was using for access to a ledge located above the busy shopping area of Oxford Street. He fell onto the ledge and from there to the ground. The ladder he was using also fell from the ledge and struck a member of the public Ms Desislava Ilieva, who was walking underneath at the time. She suffered head and back injuries. |
|
How Much? |
£35,000 plus costs across the 3 parties |
|
Who |
South West London and |
|
When |
5 March 07 |
|
Where |
City of |
|
Why |
South West London and |
|
How Much? |
£7,500 plus costs |
|
Who |
Michael Tony Mortimer |
|
When |
5 March 07 |
|
Where |
|
|
Why |
Michael Tony Mortimer of Merry Lees, |
|
How Much? |
£50,000 plus costs |